Site Handover β€” Summary Report

Project Tiger · Dhaly Infratech → Alliance Computers Limited
Report Date: 25 Oct 2026
Plan Window: 2026-08-26 → 2026-09-19
Today's Handovers: 0
100
Total Sites
96
Handed Over
4
Pending
0
In Progress
96%
% Complete
166
Open Snags
0
Today's Handovers

District-wise Progress

DistrictTotalDonePending% DoneProgress
Habiganj 10 10 0 100%
Kishoreganj 8 8 0 100%
Moulavibazar 13 13 0 100%
Narayanganj 2 2 0 100%
Narsingdi 22 22 0 100%
Sunamganj 21 21 0 100%
Sylhet 24 20 4 83.3%
TOTAL 100 96 4 96%

Daily Handover Activity

17-Aug 1 done · cum 1
30-Aug 2 done · cum 3
31-Aug 5 done · cum 8
01-Sep 13 done · cum 21
02-Sep 14 done · cum 35
03-Sep 15 done · cum 50
04-Sep 13 done · cum 63
05-Sep 9 done · cum 72
06-Sep 13 done · cum 85
07-Sep 10 done · cum 95
10-Sep 1 done · cum 96