Banglalink Alliance Computers Limited

Site HOTO Report β€” SYL_G0397

Project Tiger · Dhaly Infratech → Alliance Computers Limited · Generated 07-Sep-2026 20:21 BD time
100%Form Completion 13/15Checklist OK 5Open Snags 5Total Snags 8Photos Attached

Site & Handover Details

Site CodeSYL_G0397ZoneSylhet
HOTO Date2026-09-04DistrictSunamganj
Handover OrgDhaly Infratech LimitedTakeover OrgAlliance Computers Limited
Handover PersonMd. AnwarTakeover PersonMd. Ismail Hossain
Handover Phone01734713807Takeover Phone01847426858
Inspected ByIsmail SirajiSecurity GuardYes
Access Key Handed OverYesSite TypeGFT
BTS TypeOutdoor
Shared with OperatorYesShared Operator NameGrameen Phone

Generator Information

DG BrandMetsGenset Asset No.N/A
Capacity (KVA)22TypeCan
Fuel Tank Capacity2000Present RH1119
Fuel (no water)124 LFuel (total)124 L
Water Amount— LFuel Amount (word)One Hundred Twenty Four Liters
DG Site TypeRemoteDG Locked After FuelingYes
DG Present StatusNOK Genset ON AlarmOK
Battery BrandHamkoBattery SerialPW33WEDD0060
Battery AH100Engine SerialGU51792R
ATS BrandLocalATS ModeAuto
RH Meter TypeDigital from controllerLast Service Date2026-02-17
Key TypeLocal KeyKey Status β€” BTSLocal
Key Status β€” DG RoomOpen
Active DG1Connected Fuel Tanks1
Faulty/Disconnected DGFaulty/Disconnected Tanks

Connected Generator Checklist & Readings

ItemValueItemValue
Earth Connection OKYesLoad Current (A)30
Frequency (Hz)51.2Phase3 Phase
Output390Engine BrandPerkings
Voltage L1-L2390Voltage L2-L3389
Voltage L3-L1390Voltage L1-N226
Voltage L2-N225Voltage L3-N225
Current Line 115Current Line 215
Current Line 30N-G2.31
Controller StatusOKBlack Smoke StatusNOK
DG Battery ChargerOKATS Physical & Functional StatusOK
DG Automation (VDTC/RVDTC/Rectifier) per BL StandardOKFuel Preserved at Safe & Appropriate LocationOK
Exhaust Fan / Ventilation Sufficient When RunningOKSufficient Water in Radiator & BatteryOK
DG Radiator ConditionOKDG Battery ConditionOK
DG Runs in Both Auto & Manual ModeOKGENSET ON Alarm Functioning ProperlyOK
Lub Oil Status (Level & Colour)NOKDG RH Meter Working ProperlyOK
No Parts Missing (if missing, note in snags below)OK

Snags Found (5)

Snag #SystemCategoryComponentStatusObservationsActionPhoto
S-055 DG DG - Other DG lube oil empty Faulty Open
S-056 DG DG - Other servicing date run hour over Faulty Open
S-057 DG DG - Other Font site canopy missing Faulty Open
S-058 DG DG - Other DG back site canopy missing Faulty Charging dynamo faulty Open
S-059 DG DG - Other Need to overhaling Faulty Open

Deficiencies & Safety Remarks

DG Major Deficiencies
Safety Remarks
General Remarks

Site Photos


Site / Nameplate

DG RH / Meter

Fuel Gauge
Md. Anwar
Handed Over By · Dhaly Infratech Limited
01734713807
Date:  
Md. Ismail Hossain
Taken Over By · Alliance Computers Limited
01847426858
Date:  
 
BL Concern · Name / Signature
 
Date:  

Appendix β€” Photo Evidence (8)

Full-size reference photos for SYL_G0397, grouped by type and numbered for cross-reference against the tables above.

Required Site Photos (3)

Photo 1 β€” Site / Nameplate
Photo 2 β€” DG RH / Meter
Photo 3 β€” Fuel Gauge

Snag Evidence Photos (5)

Photo 4 β€” S-055 β€” DG lube oil empty
Photo 5 β€” S-056 β€” servicing date run hour over
Photo 6 β€” S-057 β€” Font site canopy missing
Photo 7 β€” S-058 β€” DG back site canopy missing
Photo 8 β€” S-059 β€” Need to overhaling