HOTO Tracker β€” Project Tiger

Dhaly Infratech β†’ Alliance Computers Limited DG handover & snag reconciliation
58%
58 / 100
Sites Handed Over
🚧
4
In Progress
⚠️
70
Open Snags
πŸ—‚οΈ
70
Total Snags Logged

Report Summary

Snags by Category
DG - Other 44
Structural/Civil Damage 8
DG - Mechanical/Fuel 7
DG - Controller/Electronics 5
Other/Uncategorized 3
Security/Theft/Access 1
Site Cleanliness/Bush 1
DG - Battery/Starter 1
Handover Progress by District Sort: A–Z Β· % Complete Β· Most Pending
Habiganj 8/10
Kishoreganj 1/8
Moulavibazar 12/13
Narayanganj 2/2
Narsingdi 13/22
Sunamganj 20/21
Sylhet 2/24

Handover Plan Status

Site CodeDistrictOutgoingIncomingPlannedActualStatusAction
πŸ“ Sunamganj 1 Sites
  ↳ Bishwamvarpur 1 Sites
SYL_X0274 Sunamganj DITL ACL 2026-09-07 β€” In Progress

Snag Log

Snag #SiteSystemComponentStatus FoundObservationsPhotoActionLogged
🌐 RO-2
πŸ“ Narayanganj
DHK_G4393 4 Snags 4 Open
DHK_X2727 3 Snags 3 Open